OLD becomes NEW!
Our old diesel filling station is being dismantled and optimally integrated into our site as part of the infrastructure measures.⛽️
Week 50
Biomass heating plant
27.05.23
Preparations for the tar surface!
In order to create a stable and even tar surface, our site and the heating plant are currently being bordered and brought to the same level.✅
Week 49
Biomass heating plant
20.05.23
Laying the first pipes ✅
Week 48
Biomass heating plant
14.05.23
Demolition of our old wooden hall ⛔️
In addition to the biomass heating plant, we are also expanding our infrastructure. In particular, we are focusing on optimising the road network.
Week 47
Biomass heating plant
06.05.23
In the meantime, the construction work has also reached our warehouse.
In the next few weeks, the first pipes will be laid.✅
Week 46
Biomass heating plant
26.04.23
Birds’s eye view of the heating plant
Week 45
Biomass heating plant
19.04.23
The moving floor provides the basis for our heating plant.✅
Alternating back and forth movements pull wood chips to the conveyor belt each time.
Week 44
Biomass heating plant
12.04.23
Further progress on the steel construction (steam pipe)!
➡️ At the moment, construction work is going on along our canal and the pallet hall.
Week 43
Biomass heating plant
05.04.23
Week 43: The shoring of the steel beams takes shape.✅ The next step is to create an opening into the wooden hall.➡️
Week 42
Biomass heating plant
28.03.23
Further progress on the device for steam transport 🏗
Week 41
Biomass heating plant
23.03.23
To ensure that the steam produced also reaches our machines, a device for the steam pipe is currently being assembled. The steam pipe will run several metres above the ground.
Week 40
Biomass heating plant
14.03.23
Laying of a wastewater pipe for safe drainage of the site.✅